Activity-Based Budgeting

The traditional budgeting planning methods and techniques carry much undesirable association due to some dysfunctional practices. Even when it works with a highly detailed level, it may trigger low confidence. It uses to happen because the assumptions applied in the process tend to be controversial, coming from organizational politics iterations that still arrive at unrealistic projections of expenses.

Let's start with an example.

Considered that the company X estimates receiving 100,000 sales order in the upcoming year and the cost to process one order is $2.

In the last year’s budget called for $50,000 of sales order processing expenses. Sales are expected to grow 5%

According to activity-based budgeting approach, the budget for the expenditure to process sales orders for next year will be $200,000 (Resulting from $100,000 * $2), however, considering the traditional approach, the budget would be only $52,500 ($50,000 + $2,500).

Activity-based budgeting is a planning technique where each activity has costs associated, and the expenses are estimated according to expected activity level. Different from traditional and static budgeting approaches, this technique bases its development on business operations efficiencies. It is not only a matter of inflation or business development adjustment in the previous budget. Straightforwardly, it is a method which utilizes cost driver data in the budget-setting and variance feedback processes.

During the ABB process the management will:

In this approach, the resultant budget must be based on the future workload to connect with customer requirements, organizational goals and strategies, new products and services, changes in business processes, improvements in efficiency and effectiveness, quality, flexibility, and cycle-time goals. The type, quantity, and cost of work that need to be done are the three ABB key elements.

Activity-based budgeting is more expected to be utilized by companies without historical budgeting information on which to rely. Besides, this method is more useful for new organizations Besides, or companies with new subsidiaries, new business units, new areas and so on. The company profile is the opposite from established firms, with little change in the market or an in a stable environment, which tends to use traditional budgeting approach, by applying a flat rate to the prior year budgeted amounts to reflect business growth and inflation.

The use of ABB became increasingly popular mainly due to cynicism about traditional budgeting, which tends to assume that the existing level of resources is already justified and, as part of the game, managers then lobby for even more resources. Instead, ABB calculates the resources amount by applying a reverse calculation. Also, this technique is not restricted to a 12-month planning horizon. As a result, this cost estimating method can be applied to any planning horizon. Another reason for this growing popularity is because it provides for what-if analysis, something that managers increasingly want answers for in financial terms.

Benefits

This approach allows a deeper budgeting process control and budget alignment with overall company goals. It also provides helpful details regarding projections due to the accurate planning of revenue and expense budget.

The ABB promote the focus on the company's volume and types of activities and allows a high level of detailing in cost planning.

This approach allows management to see how much cost is linked with each part of the business and then decides how much and where the resources will be allocated.

Limitations

When compared to traditional budgeting techniques, the ABB is more costly due to the amount of data required and the managers' time to analyze them, to develop the planning. Also, the accuracy could be jeopardized due to a number of assumptions and insight require from management.

As in other dynamics approach, one possible threat is the significant workload necessary to track activities and the costs linked to them, and there may be no traditional or suitable tracking systems, which would be a barrier to implement the process. It also makes the maintenance and analysis of budget variances costly due to the necessary resources (personnel and monetary)

Did you like this topic? If you like the subject and want to go further, you can find below our references.

Source:

Brimson, J. A., Antos, J., & Collins, J. (1999). Driving value using activity-based budgeting (Vol. 1). Wiley.

Hilton, R. W., Maher, M., & Selto, F. H. (2003). Cost management: strategies for business decisions. McGraw-Hill/Irwin. Chapter 17

Lalli, W. R. (Ed.). (2011). Handbook of budgeting (Vol. 562). John Wiley & Sons. Chapter 18 and 33.